Client
Clarion Housing
Site
St Georges Court, Wrotham, Kent
Duration
5 months
Services Used
Demolition
St Georges Court in Wrotham, Kent had been the subject of community and developer interest for nearly a decade, with original plans put in place back in 2014, when Circle Housing Russet Homes decided the site would benefit from demolition of the existing sheltered housing scheme to make way for affordable housing provision to better serve the local area. Delays in the project due to community dissatisfaction at the proposals, refusal of residents to relocate and a number of rejected planning applications, meant that the site has been in limbo for a number of years, only recently obtaining planning permission for an iteration of the scheme which was deemed to suit the needs of the area.
Development of the site was further complicated by the purported existence of a restrictive covenant, wherein the historic landowner had gifted the site to the village to be held for the housing needs of the elderly. This matter was only resolved when the descendants of this generous individual spoke publicly about the wishes of their ancestor, and acknowledged the changing needs of the populace.
The version of the fully affordable scheme finally approved will bring 38 high quality homes split between 12 maisonette flats with individual ground level access and 26 houses. The design utilises the local architectural vernacular but reinterprets this in a contemporary style and celebrates the character of the village which has been designated as a part of an area of outstanding natural beauty.
With demolition works completed in Autumn 2023, the site is now ready for development of new housing provision to commence in early 2024.
Following an extremely competitive tender process, Goody Demolition were awarded the contract to undertake the demolition and enabling works at the former assisted living site. The contract was procured in good time prior to the planned commencement date for practical works, due to the extensive nature of the pre-start requirements. The project had gone through many planned iterations since being vacated, and the planning approval finally granted was subject to a number of pre-commencement conditions. GDL were contracted to assume the role of Principal Contractor, and as a part of this project inherited responsibility for satisfying the planning conditions – this involved production of a Demolition Environmental Management Plan and Logistics Plan, which following consultation with, and approval from, the Principal Designer were submitting to the Local Planning Authority in a timely manner, and granted discharge to allow our works to commence.
Once on site, our scope of works included setting up exclusion zones, barriers and signage; establishment and maintenance of welfare, accommodation and suitable meeting facilities; management of service disconnections, terminations and diversions and setting up of temporary supplies required for the works; installation of 6no. bird boxes and 5no. bat boxes as per ecologists recommendation as well as designated monitoring at specified stages of the works; tree/root protection measures and tree removal/pruning as required; waste management; asbestos removal works (carried out by a specialist licensed subcontractor); internal soft strip; structural demolition to designated blocks of flats; clearance of site and placement of concrete blocks at entrances upon completion to ensure site was secure to prevent trespass prior to commencement of construction activities.
When surveyed prior to planned demolition works, a number of buildings comprising the St Georges Court site were found to be ideal locations for roosting bats and nesting birds. Ecologists were employed by the client and were asked to undertake a full inspection of the buildings on site to determine the locations most suited for roosting. The results of the survey were not unexpected – as the site had lain derelict for so long the majority of buildings showed signs of use by birds and bats, and as such, prior to demolition GDL staff had to carry out careful dismantling by hand to expose interior of the structures under watching brief under supervision by a qualified ecologist.
St Georges Court has been the subject of close scrutiny for many years, in close proximity to neighbouring properties and followed closely by news outlets and community interest groups. As a result, we knew from early stages of our involvement that we would need to wok closely with the Client, Local Authority and other stakeholders to ensure a robust, transparent approach was taken to community liaison. Initial notification letters were provided, as well as continuous updates on the project and prior notice given of any especially noisy or disruptive activities - to ensure our neighbours were kept informed regarding the progress of the works and that the impact on their daily lives was minimised as much as possible.
We’re here to assist with your demolition needs - reach out to us to get started.